If you are a project manager you can be interesting to get the workload of your resources. With > PAVONElive you can do this directly in your project plan. Open the project plan of your project and add an histogram for the desired resources of your project. First, the workload for the current project will be shown as column. But you can expand the data to show the workload for all projects. A red column shows you, that the resource is overloaded during the time. If you move the tasks to another time, the columns will be customized directly.